Custom Production Process Of Buckle

As a manufacturer generally in the production of a buckle, the first need to be divided into two situations, 1 is whether the manufacturer has a current mold, 2. There is no ready-made mold, which needs to be developed from beginning to end. 3. There is a ready-made mold, but it needs to be slightly modified and improved according to the customer's existing requirements.

 

The first situation is generally as a current mold manufacturer in the production of the relative aging of the product will be much faster, the general manufacturer in the next day after receiving the order to start the material with the material supplier, the normal material supplier is generally 1-3 days faster, the slowest is a week, this situation is very special.

 

As soon as the material arrives at the factory, the general situation is that the delivery time is about 7-10 days, and this situation also depends on the number of orders, and also depends on the manufacturer's mechanical equipment.

 

Second, the manufacturer does not have any ready-made molds, which need to be developed from scratch. In this case, several processes are required. It is necessary to draw the product diagram of the desired product first, and then compare the graphics drawn by the product. b. Measure the product size with the drawing and mark each detailed size.

 

Through the marked size, the product wire cutting or laser cutting at the same time also need wire cutting part of the product molding die, of course, this is only open a small part of the mold, so that the product into a bending molding, this is also as a customer also need to explain, not all the products can be used after wire cutting, it must also use the mold to form it, For example, bending and the like, wire cutting only reduces the blanking die of the product.

 

After cutting the mold line, assemble and form it. E. Send the wire-cut products back to the customer, and then the customer will put the products into the machinery or equipment they need to assemble, debug, and ask questions to the manufacturer. Those areas need improvement and fixing! F. Make sure that there is no problem in the whole link and carry out normal assembly line production.

 

This whole link time first drawing 3-4 days, product wire cutting 3-5, product sample delivery time 2-3 days, in which there are problems back and forth time does not count, if it needs to add 3 days, to determine no problem normal finished product production time of about 15-20 days. The whole link is 23 days according to the fast calculation, but some manufacturers in order to keep the newspaper to my customers for 25 days is also a normal thing, so you must need to understand the manufacturer when the link in this time, to put it frankly, this time is also the manufacturer does not want more time, just more than 2 days.